Interconnection Tiers

Interconnection is the connection of the RGS (renewable generation system) to the LCEC electric grid. An interconnection tier is based on the size of the RGS. Follow the steps below depending on the size of your RGS. For additional information or assistance contact LCEC Customer Care at 239-656-2300 or 1-800-599-2356 or email LCECNetMetering@lcec.net

All interconnection tiers require a Disconnect Switch. Please carefully review our Disconnect Switch Specifications before installation.

Tier One (0-10kW)

Follow these steps to participate in the program:

Step 1 Except for testing and inspection, the manual disconnect should be open. Do not begin parallel operation until after your bidirectional meter is installed.
Step 2 Review LCEC Net Metering Guidelines.
Step 3 Review the rates.
Step 4 Complete a Tier 1 interconnection agreement.
Step 5 Complete a Application and Compliance Form.
Step 6 Submit the application, interconnection agreement, and supporting documentation* to:

Portal Mail:   Email:
LCEC Customer Care Center   LCECNetMetering@lcec.net
433 N 15th St
Immokalee, FL 34142

*Supporting documentation includes: An electric one-line diagram and spec sheet of the inverter and other installed equipment. An interconnection fee of $35 will be billed to the account after the agreement is approved.

Step 7 Fax final permit approval to: 239-656-1889 or email LCECNetMetering@lcec.net
Step 8 Begin parallel operation after bidirectional meter is installed.

Tier Two (>10kW-100kW)

Follow these steps to participate in the program:

Step 7Submit the application, interconnection agreement, and supporting documentation* to:

Step 1 Except for testing and inspection, the manual disconnect switch should be open. Do not begin parallel operation until after your bidirectional meter is installed.
Step 2 Review LCEC Net Metering Guidelines.
Step 3 Review the rates.
Step 4 Contact your insurance agent and inquire about proper coverage of your renewable-power system under your policy.
Step 5 Complete the following:
Tier 2 interconnection agreement
Step 6 Complete an Application and Compliance Form.
Portal Mail:   Email:
LCEC Customer Care Center   LCECNetMetering@lcec.net
433 N 15th St
Immokalee, FL 34142

*Supporting documentation includes: An electric one-line diagram and spec sheet of the inverter and other installed equipment along with proof of insurance. You will be advised of the interconnection fee after LCEC receives and reviews your completed application and interconnection agreement. This fee will be billed to the account after the agreement is approved.

Step 8Fax final permit approval to: 239-656-1889 or email LCECNetMetering@lcec.netStep 9Begin parallel operation after bidirectional meter is installed.

Tier Three (>100kW-1MW)

Follow these steps to participate in the program:

Step 1 Except for testing and inspection, the manual disconnect switch should be open. Do not begin parallel operation until after your bidirectional meter is installed.
Step 2 Review LCEC Net Metering Guidelines.
Step 3 Review the rates.
Step 4 Contact your insurance agent and inquire about proper coverage of your renewable-power system under your policy.
Step 5 Complete a Tier 3 interconnection agreement.
Step 6 Complete an Application and Compliance Form.
Step 7 Submit the application, interconnection agreement, and supporting documentation* to:

Portal Mail:   Email:
LCEC Customer Care Center   LCECNetMetering@lcec.net
433 N 15th St
Immokalee, FL 34142

*Supporting documentation includes: An electric one-line diagram and spec sheet of the inverter and other installed equipment along with proof of insurance. An application fee of $1,000 will be required to process the interconnection request.

Step 8 Fax final permit approval to: 239-656-1889 or email LCECNetMetering@lcec.net
Step 9 Begin parallel operation after bidirectional meter is installed.
NOTICE: You are leaving the LCEC website

By selecting the “Continue” button below you will be leaving the LCEC website and entering a website hosted by another party. Please be advised that you will no longer be subject to, or under the protection of the LCEC website Privacy Policy, and that LCEC is not responsible for the content or accuracy of the information on the website. We encourage you to review the privacy policy on the site you are entering before providing any personally identifiable or confidential information.

NOTICIA: Usted está saliendo de la página de internet de LCEC.

Seleccionando el boton “Continuar” ud. estará saliendo de la página de internet de LCEC e ingresará a una página de internet acogida por una compañia tercera. Por favor note que ud. no estará sujeto a o bajo la protección y reglas de privacidad de la página de internet de LCEC. LCEC no es responsable por el contenido y veracidad de la información en la página de internet. Antes de proceder y proveer cualquier información personal o confidencial, le sugerimos que revise las reglas de privacidad en el sitio de internet al que ud. está ingresando.